Tampa International Airport: Steel Renovation Project
This multimillion dollar design build coatings project began with the formation of the Service Painting Corporation Design Build Team. By assembling a general contractor, architectural firm, coating’s consultants and inspectors, Service Painting Corporation built a team which earned the right to perform this extraordinary, complicated project.
Design for the actual coatings processes included the design and erection of a massive portable containment system which enabled Service Painting Corporation to work around the clock because of FAA regulations and a 60 day construction schedule.
Project Scope:
Air side “F” Shuttle System
Paint structural steel under guideways.
Paint structural steel under pedestrian walkway; 300,000 square feet plus
Pressure clean concrete piers.
Pressure clean metal fascia panels.
Bearing pad inspection and repairs.
Paint edge angles in the truck court area.
Air side “F” Building
Refurbish exterior exit stairs.
Refurbish exterior roof structural steel.
Pressure clean and coat CMU walls.
Refurbish exterior building doors.
Caulk exterior glass block walls.